Have your say
Oakland International
Wind Energy Scheme

Milestones

Many different activities will need to be undertaken during the development of an onsite wind turbine in addition to consultations and studies.

Screening Request : 27th Nov 2007

This was the formal request for a Screening Opinion, in order to estabish whether an Environmental Impact Assessment would be required to support the planning application.

Met Mast Application : 1st Feb 2008

A planning application for a met mast was submitted in February 2008. The mast is used to gather essential local information about the wind energy resource at Oakland International.  The application was approved in May 2008.

Request scoping report from Borough Council : 1st Apr 2008

Having established that an Environmental Impact Assessment was required, Wind Direct then contacted the council in order to agree the scope of the assessment. In this case, it was decided that noise and landscape were the most important issues.

Met Mast Installation : 10th Jun 2008

Following planning approval, a  60m met mast was installed in June 2008 and has been gathering information about the wind speed and direction at Oakland.  Have you seen it?

Planning Application Submission : Expected Early 2010

Once the public consultation has finished, we hope to submit a planning application and accompanying Environmental Statement showing the findings of our assessments in November 2008.

Planning Determination : Expected Early 2010

Bromsgrove District Council will have a statutory obligation to determine planning applications within 16 weeks.  However, in practice it can often take longer. 

Construction starts (if consented) : Expected Late 2010

Once started, the total construction time will take about 6 months.

Energise : Expected Early 2011

Once the wind farm is built, the turbines are then connected to Oakland International and all electrical systems tested.  When this is all in order, the wind farm be 'energised' and will start generating electricity.

Mast erection

Mast erection

Home - About Wind Direct - The Wind Energy Scheme - Facts & figures - Why here? - Predicted views - Community benefits - What's happening? - Community - Consultees - Studies - Milestones - The process - Feasibility - Construction - Operation - Oakland International - Values & history - How we work - Wind energy - FAQ's - Education - Links - Picture gallery - Contact us - Have your say - Search - Terms, Conditions & Disclaimer

Copyright © 2010 - Wind Prospect Ltd

Content Management System and Database DesignContent Management System and Database Design