Have your say
Oakland International
Wind Energy Scheme

What's happening?

This page will keep you up to date with how things are changing and the latest plans.  Expected dates of activities are an approximate best guess.

Activity Actual Date Expected Date Detail
Screening Request 27th November 2007 Milestone
Met Mast Application 1st February 2008 Milestone
Ecology Study 20th March 2008 Study
Request scoping report from Borough Council 1st April 2008 Milestone
Met Mast Installation 10th June 2008 Milestone
Leaflet to nearby homes 15th August 2008 Community
Public consultation 12th September 2008 Community
Planning Application Submission   Early 2010 Milestone
Planning Determination   Early 2010 Milestone
Construction starts (if consented)   Late 2010 Milestone
Energise   Early 2011 Milestone
Oakland International

Oakland International

Home - About Wind Direct - The Wind Energy Scheme - Facts & figures - Why here? - Predicted views - Community benefits - What's happening? - Community - Consultees - Studies - Milestones - The process - Feasibility - Construction - Operation - Oakland International - Values & history - How we work - Wind energy - FAQ's - Education - Links - Picture gallery - Contact us - Have your say - Search - Terms, Conditions & Disclaimer

Copyright © 2012 - Wind Prospect Ltd

Content Management System and Database Design BristolContent Management System and Database Design Bristol